Keck back on schedule after delay
- Author:
- Borg, Jim
- Title:
- Keck back on schedule after delay
- Periodical:
- The Honolulu Advertiser
- Year:
- 1989
- Volume:
- V5
- Pages:
- 32
- Subject:
- Keck Construction
- Summary:
- A 10-month delay was caused by a change in mirror manufacturing. Itek Optical Systems in Lexinton, Mass. has been working on "stress polish" the mirror but recently changed to use "warping harnesses" to accomplish the final product.
- Date:
- February 5, 1989
- Collection:
- Akiyama